EV Charger Installation from Application to Complete Installation in a Residential Development - Time Spent 3 Months 12 Days

Successful Case 1:

Application to Building incorporated Owner to get consent for taking electricity from Main Switchboard on 11 January 2024 and Approval obtained on 28 February 2024 after IO Meeting.

Submit Schematic Diagram to CLP for Approval on 12 March 2024 and Approval obtained on 10 April 2024.

32A 3-Phase (22kW) Fast-Charge Installation completed and Electricity Meter installed by CLP on 23 April 2024.

Remark:

  • NO application made to Environmental Protection Department

  • Cost 100% paid by owner without any Subsidise

  • Single Appointment for EV Charger Installation including consultancy fee, insurance, liaison with BMO & CLP, etc.

  • Monthly saving of HK$4,000 Fuel compare with Petrol vs Electricity

For Enquiry, please email to us at info@pine-bridge.com.hk

Moving our steps to participate meeting the Mile Stone of having more EV Charger in HKSAR!!!!!!!

Disclaimer:

  • This do not have any relation with EV Charger at Home Subsidy Scheme (EHSS) under Environmental Protection Department (EPD)

Next
Next

Definitions of Final Circuit/Distribution Circuit/Distribution Board in BS7671:2018 – IET Wiring Regulations